Pasatiempo Water Treatment Facility

Water Infrastructure Built for Reliable Performance

CompletedGeneral Contractor (GC)

Construction of an integrated non-potable water treatment and storage system for Pasatiempo Golf Club. The scope included a 500,000-gallon cast-in-place concrete storage tank and supporting mechanical systems for irrigation.

ClientPasatiempo Golf Club
LocationSanta Cruz, CA
ArchitectSSA Landscape Architects
System500,000-gallon water storage

Challenge

The project required coordinating multiple water sources, treatment components, and distribution systems to ensure reliable irrigation while meeting performance and operational requirements. Sequencing and system integration needed to be carefully managed to ensure the facility operated as designed.

Approach

Bogard coordinated the construction of the tank, pump systems, filtration equipment, and supporting structures to ensure proper integration and operation. Close coordination with the design team and stakeholders supported efficient sequencing and accurate installation of civil and mechanical components.

Field supervision emphasized quality control, constructability, and system performance throughout the build.

Result

The completed facility provides reliable storage and delivery of non-potable water for irrigation, supporting long-term water management goals and consistent performance.

“I have never worked with a better GC or Project Manager...you guys do incredible work.”
Willie SlingerlandRegional Sales Manager, Watertronics (Subcontractor to Bogard)